Platform as code (Milestone 2)

Assignment

"The board wants to see that you can rebuild the platform at any time," Simone Wyss writes. "Throw it away in front of them and build it again, with the bike shop's web shop and room for another member."

Milestone 2 covers part 4. In the base you build a Kubernetes cluster from code on your cloud, roll out the web shop with GitOps and give the members namespaces from a template. In the advanced tasks you rebuild the platform, add a member of your own and protect the branch main. Milestone 2 belongs with milestone 1 to hand-in 1.

Everything runs in your own lab with your personal parameters from chapter 0.3. The base has seven requirements.

  1. The two cluster VMs come from OpenTofu in your repo platform, tofu plan shows no changes afterwards, and the state is not in Git.
  2. The k3s cluster runs with a server, an agent and host-gw routing, and kubectl works from the front-end.
  3. Gitea runs on the front-end with the private repo wolkenwerk/platform, and Argo CD reads it with a read-only token.
  4. Argo CD rolls out the web shop from Git, and you show self-heal and a change through Git.
  5. The namespaces velo and gemeinde come from the template with ResourceQuota, LimitRange and NetworkPolicy.
  6. The municipality's ResourceQuota uses your personal values and arrives through a pull request.
  7. You show the quota at its limit and the separation of the namespaces by the NetworkPolicy, and the check m2 is green.

You prove the base with the report of the check m2 and one screenshot per requirement, each with a file name that starts with the number of its requirement. python3 ~/cc/checks/check.py m2 writes the report on the front-end. For a pull request, a screenshot from Gitea with the diff and the merge is enough.

Plan four to six hours for the three advanced tasks. Each one is worth 0 to 3 points by the levels of the advanced tasks. Every task you do needs documentation in five parts. Chapter 4.6 explains the concepts behind them and lists the requirements of each task.

You tear the cluster down with tofu destroy, rebuild it with tofu apply and the Argo CD bootstrap, and measure the time from the start of the teardown to the first answer of the web shop. Along the way you explain what state and drift mean for a rebuild. In the lab, with the platform as it stood after part 4, the web shop ran again after just under three minutes. Start the rebuild early in the showing and explain the code while it runs. Chapter 4.6 describes the task.

One more member of your choice gets a namespace from the template through a pull request, with limits of your own that you justify. You also create an Argo CD AppProject that allows only this member's namespace. Chapter 4.6 describes the task, and you know the template from chapter 4.5.

In Gitea you protect the branch main so that changes only get in through a reviewed pull request. You show that Gitea rejects a direct push. Chapter 4.6 describes the task.

You show the advanced tasks live in class or in a screencast of at most ten minutes. For a live showing you book a slot with your instructor yourself. It must take place by hand-in 1. The screencast starts with cat /etc/cc-lab.env and the report of the check m2 with its hash and your two questions, which you answer during the showing.

The folder m2/ of your hand-in repo holds the screenshots of the base. The advanced tasks add their documentation and platform/, a copy of your repo platform from Gitea without the .git folder, state, tokens or passwords. The showing adds the screencast or a link to it.

You put the reports of the checks in reports/. The overview describes how the repo is structured and how you set a tag.

Base requirementPoints
Cluster VMs from OpenTofu, plan without changes, state outside Git3
k3s with server, agent and host-gw, kubectl from the front-end3
Gitea with a private repo, read-only token for Argo CD3
Web shop with Argo CD, self-heal and a change through Git3
Namespaces velo and gemeinde from the template3
The municipality's ResourceQuota with the personal values through a pull request3
Quota at the limit and NetworkPolicy shown, check m23
Base21
Advanced taskPoints
Rebuilding the platform with the measured time (Task A)3
A member of your own with an AppProject (Task B)3
Protection of the branch main (Task C)3
Advanced9

Milestone 2 is worth up to 30 points in total. A base requirement gets 3 points when the report and a screenshot prove it, 2 points when the check is green but a fitting screenshot is missing, and 1 point when it is only partly met. Each of the two questions you leave unanswered or answer wrongly costs 1 point of the advanced tasks. If the documentation or one of its parts 1, 2, 4 and 5 is missing, an advanced task gets at most 1 point.